RAMS template: risk assessment and method statement
Fill in one document for one job: the hazards and who could be harmed, the controls, the sequence of works step by step, PPE, emergency arrangements and sign-off, with a list for the people who have been briefed. Download it as a PDF; nothing is uploaded.
RAMS (risk assessment and method statement) is a trade term rather than a legal one. The legal duty is the risk assessment: under regulation 3 of the Management of Health and Safety at Work Regulations 1999 employers must make a suitable and sufficient assessment of the risks to their employees and to other people, and record the significant findings if they employ five or more. A method statement is good practice for most work; HSE says arrangements for demolition, dismantling or structural alteration must be recorded in writing before the work begins.
Free PDFs carry a small “Free version” mark. Pro removes it, saves your certificates, adds your logo and company details and reminds you before renewals.
Important: this tool records the results and findings you enter and formats them as a document. It does not inspect, test or assess anything. Competence and compliance remain with the user. Not legal advice.
What RAMS means and what the law requires
| Part | What it is | Legal position | Source |
|---|---|---|---|
| Risk assessment | Identify what could cause harm, decide who could be harmed and how seriously, and eliminate the hazard or control the risk | A legal duty: a suitable and sufficient assessment, reviewed if it may no longer be valid; significant findings recorded for five or more employees | Management of Health and Safety at Work Regulations 1999, regulation 3; HSE, Managing risks and risk assessment at work |
| Method statement | Describes in a logical sequence how a job is carried out safely, with all the control measures | Not required by law for most work. Arrangements for demolition, dismantling or structural alteration must be recorded in writing before work begins, usually as a method statement | HSE, Construction: Administration |
| RAMS | The two combined in one document, often asked for by a client or principal contractor | Not a legal term. It does not appear on the HSE pages cited here | Our reading of the HSE pages, 18 November 2026 |
Method statement template: the sequence of works
HSE describes a method statement as setting out exactly how a job is to be carried out, in a logical sequence, including all the control measures, and says it can be generated from the risk assessment. On this form each step has the work, the controls and checks that apply, and who does it.
HSE also says the statement will be similar from job to job for a repeated operation, but should be revised if circumstances change markedly.
How to fill in the RAMS
- Describe the job, the site and the equipment, and list who else is working nearby.
- List the hazards of this job. HSE warns that copying an example and adding your company name would not satisfy the law, so think about the real hazards on this site.
- For each hazard say who could be harmed and how, rate the risk, write the controls and rate the risk that remains.
- Write the steps of the work in order, with the control or check that goes with each step.
- Add PPE as the last line of defence after the other controls, and the emergency arrangements.
- Sign it, get it approved if the client or principal contractor asks, and have everyone doing the work sign that they have read it.
Free RAMS template: what is in the PDF
- Job details, scope of the work, plant and equipment.
- Risk assessment table: hazard, who could be harmed and how, risk before, control measures, risk after, who is responsible.
- Method statement table: step, what is done and how, controls and checks, who.
- PPE and welfare checks, emergency arrangements, preparer and approver with a review date.
- A signature list for the operatives briefed.
Sources
- The Management of Health and Safety at Work Regulations 1999, regulation 3: legislation.gov.uk, uksi/1999/3242/regulation/3, read 18 November 2026.
- HSE, Managing risks and risk assessment at work: hse.gov.uk/simple-health-safety/risk, read 18 November 2026.
- HSE, Risk assessment: Template and examples: hse.gov.uk/simple-health-safety/risk/risk-assessment-template-and-examples.htm, read 18 November 2026.
- HSE, Construction: Administration, Risk assessments and Method statements: hse.gov.uk, construction/safetytopics/admin.htm, read 18 November 2026.
- Own layout and wording; not an official HSE form and not issued by any scheme or client.
Writing certificates every week? Pro is £39/month ex VAT
- Every certificate saved: fire alarm, emergency lighting, PAT, EIC, EICR and Minor Works
- Your logo, company, accreditation and signature on every PDF
- History with search, copy and re-issue
- Renewal reminders in the app and in your calendar
- No “Free version” mark
Business (£79/month ex VAT) adds up to 5 users, a client and site register and bulk reminders. Plans are for businesses (sole traders, partnerships and companies). The forms and calculators stay free.
Frequently asked questions
Is a RAMS a legal requirement?
The term is not in the law. The risk assessment part is: employers and certain self-employed people must make a suitable and sufficient assessment of the risks. A method statement is good practice for most work, but arrangements for demolition, dismantling or structural alteration must be recorded in writing before the work begins.
What is the difference between a risk assessment and a method statement?
A risk assessment identifies hazards, who could be harmed and the controls. A method statement says how the job will be carried out step by step, with those controls included. HSE says a method statement can be generated from the risk assessment.
Can I reuse the same RAMS on every job?
Use it as a starting point only. HSE says copying an example would not satisfy the law; the assessment has to reflect the hazards and controls of the actual site and work, and be revised if circumstances change.
Who has to sign a RAMS?
The law does not set this. In practice the person who prepared it signs, the client or principal contractor may approve it, and the operatives sign to show they have read and understood it. The form has places for each.
How long should a RAMS be?
As long as the job needs. A simple job can fit on a few lines per table; a higher-risk or unusual job needs more detail in the sequence of works.
Can I get a reminder before the next date?
Yes, with Pro or Business. Save the record to your account and its next due date appears in your due list and calendar feed. Business also shows it per property in the register.
Is anything I type uploaded?
Not unless you choose to save it. The form, the checker and the PDF run in your browser on your device, and a draft stays in your browser’s local storage. Only when you are signed in to a Pro or Business plan and press “Save to account” is the record stored on our server, where its next due date feeds your reminders.